Delhi–Mumbai Expressway

Delayed· 1186 days lateUnionNot yet verified · researched from public reports

An access-controlled expressway from Delhi to Mumbai through Haryana, Rajasthan, Madhya Pradesh, Gujarat and Maharashtra, built in 54 packages by NHAI.

Project details
LevelUnion
WhereDelhi to Mumbai, 1,445 km including spurs (Haryana, Rajasthan, Madhya Pradesh, Gujarat, Maharashtra)
Ministry / departmentMinistry of Road Transport and Highways
Implementing agencyNational Highways Authority of India (NHAI)
SectorRoads
Spent₹71,718 cr
StatusWork in progress
Status as of31 Mar 2026

All key dates

  1. Original target31 Dec 2024
  2. Revised target31 Oct 2025
  3. Delhi–Vadodara section target30 Jun 2026
  4. Second revised target31 Mar 2028

Why it is delayed

Stuck at: Three Gujarat packages (87 km) on the Vadodara–Virar section, held by Roadway Solutions India Infra LtdNHAI cites the contractor's non-performance and contractual disputes on the three Gujarat packages; the contractor cites delays by NHAI in handing over land.

Environmental impact

Near the buffer zone of Ranthambore Tiger Reserve, a 12 km stretch was built as India's first wildlife corridor on a national highway, designed with the Wildlife Institute of India: five animal overpasses and a long underpass let tigers, leopards and bears cross safely, with noise barriers along the road. It opened in June 2025.

About the project

In July 2024 the Government told the Rajya Sabha that the 53 packages (1,386 km) would be finished by October 2025. In December 2025 the target moved to 2027-28; the Union Minister said this was about three years later than the original 2024 deadline. A Lok Sabha reply in December 2025 put spending at ₹71,718 crore. In March 2026 the Government counted 54 packages over 1,445 km (including spurs), of which 929 km was open to traffic; the Delhi–Vadodara section was due by June 2026 and three lagging Gujarat packages by March 2028. Targets announced only as a month or a year are shown as the last day of that month or year.

Report an update or correction

New progress, a revised date, a change of contractor or officer, or a mistake here? Share it with a link to proof.