Mumbai–Ahmedabad High Speed Rail (bullet train)
India's first high-speed rail line: 508 km from Mumbai's Bandra-Kurla Complex to Sabarmati in Ahmedabad, through Maharashtra and Gujarat.
| Level | Union |
|---|---|
| Where | Mumbai (Bandra-Kurla Complex) to Sabarmati (Ahmedabad), 508 km |
| Ministry / department | Ministry of Railways |
| Implementing agency | National High Speed Rail Corporation Ltd (NHSRCL) |
| Sector | Railways |
| Sanctioned | ₹1,08,000 cr |
| Spent | ₹90,966 cr |
| Status | Work in progress · 61% done |
| Status as of | 30 Jun 2026 |
All key dates
- Original target31 Dec 2023
- Gujarat section (Vapi–Sabarmati) target31 Dec 2027
- Revised target31 Dec 2029
Why it is delayed
Environmental impact
In 2022 the Bombay High Court allowed about 22,000 mangrove trees to be cut for the corridor (about 13.4 hectares of mangrove land affected), with replanting at a 1:5 ratio. In August 2026 it allowed 847 more mangroves to be cut for a power line feeding the corridor in Palghar, but said replanting hundreds of kilometres away (in Solapur) does not restore the local ecology, and that it will not permit such distant compensation in future.
About the project
Built with Japanese technology and loans from JICA. The 2015 JICA feasibility report expected completion in 2023. In March 2023 the Government told the Rajya Sabha that land acquisition in Maharashtra had been delayed, which delayed contracts, and that COVID-19 had also slowed the work. In July 2025 the Railway Minister said the Gujarat section (Vapi–Sabarmati) was planned for December 2027 and the full line for December 2029. MoSPI's monthly monitoring for June 2026 reported 61% physical progress and about ₹90,966 crore spent. Targets announced only as a month or a year are shown as the last day of that month or year.
Sources
- Rajya Sabha — answer on the Mumbai–Ahmedabad High Speed Rail, 31 March 2023
- Swarajya — Gujarat section by end-2027, entire route by December 2029, says Centre
- Swarajya — 61% physical progress, ₹90,966 crore spent (MoSPI flash report)
- SCC Online — Bombay HC allows felling of about 22,000 mangroves for the bullet train (Dec 2022)
- Free Press Journal — Bombay HC clears felling of 847 mangroves; distant afforestation cannot replace local ecology (Aug 2026)