Mumbai–Ahmedabad High Speed Rail (bullet train)

Delayed· 2192 days lateUnionNot yet verified · from official data

India's first high-speed rail line: 508 km from Mumbai's Bandra-Kurla Complex to Sabarmati in Ahmedabad, through Maharashtra and Gujarat.

Project details
LevelUnion
WhereMumbai (Bandra-Kurla Complex) to Sabarmati (Ahmedabad), 508 km
Ministry / departmentMinistry of Railways
Implementing agencyNational High Speed Rail Corporation Ltd (NHSRCL)
SectorRailways
Sanctioned₹1,08,000 cr
Spent₹90,966 cr
StatusWork in progress · 61% done
Status as of30 Jun 2026

All key dates

  1. Original target31 Dec 2023
  2. Gujarat section (Vapi–Sabarmati) target31 Dec 2027
  3. Revised target31 Dec 2029

Why it is delayed

Delay in land acquisition in Maharashtra and the resulting delay in awarding contracts, and the impact of COVID-19 (Government's answer in the Rajya Sabha, 31 March 2023).

Environmental impact

In 2022 the Bombay High Court allowed about 22,000 mangrove trees to be cut for the corridor (about 13.4 hectares of mangrove land affected), with replanting at a 1:5 ratio. In August 2026 it allowed 847 more mangroves to be cut for a power line feeding the corridor in Palghar, but said replanting hundreds of kilometres away (in Solapur) does not restore the local ecology, and that it will not permit such distant compensation in future.

About the project

Built with Japanese technology and loans from JICA. The 2015 JICA feasibility report expected completion in 2023. In March 2023 the Government told the Rajya Sabha that land acquisition in Maharashtra had been delayed, which delayed contracts, and that COVID-19 had also slowed the work. In July 2025 the Railway Minister said the Gujarat section (Vapi–Sabarmati) was planned for December 2027 and the full line for December 2029. MoSPI's monthly monitoring for June 2026 reported 61% physical progress and about ₹90,966 crore spent. Targets announced only as a month or a year are shown as the last day of that month or year.

Report an update or correction

New progress, a revised date, a change of contractor or officer, or a mistake here? Share it with a link to proof.

Sign in to report a project or an update.