Navi Mumbai International Airport — Phase 1
The second international airport for the Mumbai region, India's largest greenfield airport project, built under public-private partnership.
| Level | State |
|---|---|
| Where | Navi Mumbai, Raigad district, Maharashtra |
| Ministry / department | CIDCO, Government of Maharashtra (with Ministry of Civil Aviation approvals) |
| Implementing agency | Navi Mumbai International Airport Pvt Ltd (Adani Airports Holdings and CIDCO) |
| Sector | Aviation |
| Spent | ₹19,650 cr |
| Status | Completed · 100% done |
All key dates
- Completed8 Oct 2025
- Commercial flights began25 Dec 2025
Environmental impact
The site needed the Ulwe river to be diverted, a hill to be levelled and mangroves on the site to be cleared. The environmental clearance (2010) came with 32 conditions, including compensatory mangrove planting (about 350 hectares at Dahanu); the Gadhi river was left untouched after the runway layout was changed. Environmentalists warned of flood risk in the low-lying area.
About the project
Phase 1 was built at a cost of ₹19,650 crore and inaugurated by the Prime Minister on 8 October 2025. Commercial flights began on 25 December 2025. At full build-out the airport is planned for 90 million passengers a year.