| Level | Union |
|---|---|
| Where | Mandapam to Rameswaram (Pamban island), Ramanathapuram district, Tamil Nadu |
| Ministry / department | Ministry of Railways |
| Implementing agency | Rail Vikas Nigam Ltd (RVNL) |
| Sector | Railways |
| Spent | ₹535 cr |
| Status | Completed · 100% done |
All key dates
- Completed6 Apr 2025
About the project
Construction began in 2020. The old bridge was closed to trains in December 2022 because of severe corrosion. The new bridge was built for about ₹535 crore and inaugurated by the Prime Minister on 6 April 2025.
Report an update or correction
New progress, a revised date, a change of contractor or officer, or a mistake here? Share it with a link to proof.
Sign in to report a project or an update.