Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT section

Completed· 365 days lateUnionNot yet verified · researched from public reports

The last 102.9 km of the Western Dedicated Freight Corridor, linking it to Jawaharlal Nehru Port. With it, the freight-only corridor from Dadri (near Delhi) to the port was complete.

Project details
LevelUnion
WhereNew Saphale (Vaitarna) to Jawaharlal Nehru Port, 102.9 km, Maharashtra
Ministry / departmentMinistry of Railways
Implementing agencyDedicated Freight Corridor Corporation of India Ltd (DFCCIL)
SectorRailways
StatusCompleted · 100% done

All key dates

  1. Original target31 Mar 2025
  2. Revised target31 Dec 2025
  3. Second revised target31 Mar 2026
  4. Completed31 Mar 2026

Why it is delayed

Land acquisition and encroachments, then pending signalling and overhead electrification works.

About the project

The section was first due in March 2025, then December 2025. Land acquisition and encroachments delayed it, and later the signalling and overhead electrification work. DFCCIL announced the Western Dedicated Freight Corridor complete on 31 March 2026, when this section came into operation. Targets announced only as a month or a year are shown as the last day of that month or year.