Project tracker
Public projects announced or started by the Union, State, district, tehsil/taluka and local governments: budget, contractor, key dates, officer in charge, progress, and where and why a project is stuck.
Ongoing projects · Karnataka (1)
Swipe sideways to see all columns →
| Project | Status | Key date | Budget | Tender awarded to | Officer in charge | Where it is stuck · why | Environmental impact | Opinion / debate |
|---|---|---|---|---|---|---|---|---|
| Bengaluru Suburban Rail ProjectStateRailwaysNot yet verifiedBengaluru, KarnatakaRail Infrastructure Development Company (Karnataka) Ltd (K-RIDE) | Delayed· 1186 days lateWork in progress | Target31 Mar 2030Originally 31 Dec 2026 Bengaluru Suburban Rail Project All key dates
| Sanctioned: ₹15,767 crRevised: ₹16,876 cr | — | — | Stuck at: Corridors 2 and 4: the civil contractor (L&T) left; K-RIDE re-tendered Corridor 2The main contractor left the corridor contracts and the work had to be re-tendered; land for Corridor 1 is still to be acquired. | — |
Completed and closed projects (0)
Finished projects with all their details, including how late they were against the original target.
No projects match these filters yet.
Know a project that is missing?
Tell us the project's name, place, budget, dates and status, and link to proof (a government order, tender notice, news report or photo). The admin checks it before it appears.
Sign in to report a project or an update.
Only real projects are listed. Every project links to its source: an official dataset or document, or evidence shared by a member. Each stays marked “Not yet verified” until the admin has checked it. Schedule health is calculated automatically from the published dates and progress.