Public projects announced or started by the Union, State, district, tehsil/taluka and local governments: budget, contractor, key dates, officer in charge, progress, and where and why a project is stuck.

Reset

Ongoing projects · Karnataka (1)

Swipe sideways to see all columns →

Ongoing projects
ProjectStatusKey dateBudgetTender awarded toOfficer in chargeWhere it is stuck · whyEnvironmental impactOpinion / debate
Bengaluru Suburban Rail ProjectStateRailwaysNot yet verifiedBengaluru, KarnatakaRail Infrastructure Development Company (Karnataka) Ltd (K-RIDE)Delayed· 1186 days lateWork in progress
Target31 Mar 2030Originally 31 Dec 2026

Bengaluru Suburban Rail Project

All key dates

  1. Original target31 Dec 2026
  2. Revised target31 Dec 2027
  3. Corridor 2 (Mallige line) planned opening31 Dec 2028
  4. Second revised target31 Mar 2030
Sanctioned: ₹15,767 crRevised: ₹16,876 cr——Stuck at: Corridors 2 and 4: the civil contractor (L&T) left; K-RIDE re-tendered Corridor 2The main contractor left the corridor contracts and the work had to be re-tendered; land for Corridor 1 is still to be acquired.—

Completed and closed projects (0)

Finished projects with all their details, including how late they were against the original target.

No projects match these filters yet.

Know a project that is missing?

Tell us the project's name, place, budget, dates and status, and link to proof (a government order, tender notice, news report or photo). The admin checks it before it appears.

Sign in to report a project or an update.

Only real projects are listed. Every project links to its source: an official dataset or document, or evidence shared by a member. Each stays marked “Not yet verified” until the admin has checked it. Schedule health is calculated automatically from the published dates and progress.