Completed and closed projects
ProjectStatusKey dateBudgetTender awarded toOfficer in chargeWhere it is stuck · whyEnvironmental impactOpinion / debate
Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT sectionUnionRailwaysNot yet verifiedNew Saphale (Vaitarna) to Jawaharlal Nehru Port, 102.9 km, MaharashtraDedicated Freight Corridor Corporation of India Ltd (DFCCIL)Completed· 365 days lateCompleted100% done
Completed31 Mar 2026

Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT section

All key dates

  1. Original target31 Mar 2025
  2. Revised target31 Dec 2025
  3. Second revised target31 Mar 2026
  4. Completed31 Mar 2026
———Land acquisition and encroachments, then pending signalling and overhead electrification works.—
Delhi–Ghaziabad–Meerut Namo Bharat (RRTS) corridorUnionUrban transportNot yet verifiedSarai Kale Khan (Delhi) to Modipuram (Meerut), 82 kmNational Capital Region Transport Corporation (NCRTC)CompletedCompleted100% done
Completed22 Feb 2026

Delhi–Ghaziabad–Meerut Namo Bharat (RRTS) corridor

All key dates

  1. Priority section opened20 Oct 2023
  2. Completed22 Feb 2026
Sanctioned: ₹30,274 cr————
Udhampur–Srinagar–Baramulla Rail Link (USBRL)UnionRailwaysNot yet verifiedUdhampur to Baramulla, 272 km, Jammu and KashmirNorthern RailwayCompleted· 6489 days lateCompleted100% done
Completed6 Jun 2025

Udhampur–Srinagar–Baramulla Rail Link (USBRL)

All key dates

  1. Original target31 Aug 2007
  2. Completed6 Jun 2025
Sanctioned: ₹1,500 crRevised: ₹43,780 cr————
New Pamban rail bridgeUnionRailwaysNot yet verifiedMandapam to Rameswaram (Pamban island), Ramanathapuram district, Tamil NaduRail Vikas Nigam Ltd (RVNL)CompletedCompleted100% done
Completed6 Apr 2025

New Pamban rail bridge

All key dates

  1. Completed6 Apr 2025
Spent: ₹535 cr—————

Know a project that is missing?

Tell us the project's name, place, budget, dates and status, and link to proof (a government order, tender notice, news report or photo). The admin checks it before it appears.

Sign in to report a project or an update.

Only real projects are listed. Every project links to its source: an official dataset or document, or evidence shared by a member. Each stays marked “Not yet verified” until the admin has checked it. Schedule health is calculated automatically from the published dates and progress.