Project tracker

Public projects announced or started by the Union, State, district, tehsil/taluka and local governments: budget, contractor, key dates, officer in charge, progress, and where and why a project is stuck.

Reset

Ongoing projects (3)

Swipe sideways to see all columns →

Ongoing projects
ProjectStatusKey dateBudgetTender awarded toOfficer in chargeWhere it is stuck · whyEnvironmental impactOpinion / debate
Mumbai–Ahmedabad High Speed Rail (bullet train)UnionRailwaysNot yet verifiedMumbai (Bandra-Kurla Complex) to Sabarmati (Ahmedabad), 508 kmNational High Speed Rail Corporation Ltd (NHSRCL)Delayed· 2192 days lateWork in progress61% done
Target31 Dec 2029Originally 31 Dec 2023

Mumbai–Ahmedabad High Speed Rail (bullet train)

All key dates

  1. Original target31 Dec 2023
  2. Gujarat section (Vapi–Sabarmati) target31 Dec 2027
  3. Revised target31 Dec 2029
Sanctioned: ₹1,08,000 crSpent: ₹90,966 cr——Delay in land acquisition in Maharashtra and the resulting delay in awarding contracts, and the impact of COVID-19 (Government's answer in the Rajya Sabha, 31 March 2023).In 2022 the Bombay High Court allowed about 22,000 mangrove trees to be cut for the corridor (about 13.4 hectares of mangrove land affected), with replanting at a 1:5 ratio. In August 2026 it allowed 847 more mangroves to be cut for a power line feeding the corridor in Palghar, but said replanting hundreds of kilometres away (in Solapur) does not restore the local ecology, and that it will not permit such distant compensation in future.
Delhi–Mumbai ExpresswayUnionRoadsNot yet verifiedDelhi to Mumbai, 1,445 km including spurs (Haryana, Rajasthan, Madhya Pradesh, Gujarat, Maharashtra)National Highways Authority of India (NHAI)Delayed· 1186 days lateWork in progress
Target31 Mar 2028Originally 31 Dec 2024

Delhi–Mumbai Expressway

All key dates

  1. Original target31 Dec 2024
  2. Revised target31 Oct 2025
  3. Delhi–Vadodara section target30 Jun 2026
  4. Second revised target31 Mar 2028
Spent: ₹71,718 cr———Stuck at: Three Gujarat packages (87 km) on the Vadodara–Virar section, held by Roadway Solutions India Infra LtdNHAI cites the contractor's non-performance and contractual disputes on the three Gujarat packages; the contractor cites delays by NHAI in handing over land.Near the buffer zone of Ranthambore Tiger Reserve, a 12 km stretch was built as India's first wildlife corridor on a national highway, designed with the Wildlife Institute of India: five animal overpasses and a long underpass let tigers, leopards and bears cross safely, with noise barriers along the road. It opened in June 2025.
Zojila TunnelUnionRoadsNot yet verifiedBaltal (Jammu and Kashmir) to Minamarg (Ladakh)National Highways and Infrastructure Development Corporation Ltd (NHIDCL)Delayed· 517 days lateWork in progress64% done
Target29 Feb 2028Originally 30 Sept 2026

Zojila Tunnel

All key dates

  1. Original target30 Sept 2026
  2. Revised target29 Feb 2028
Sanctioned: ₹6,809 crSpent: ₹3,934.42 cr——COVID-19 disruptions, a terrorist attack at the nearby Sonamarg tunnel project, and long spells of harsh weather (Union Minister, Lok Sabha).—

Completed and closed projects (4)

Finished projects with all their details, including how late they were against the original target.

Swipe sideways to see all columns →

Completed and closed projects
ProjectStatusKey dateBudgetTender awarded toOfficer in chargeWhere it is stuck · whyEnvironmental impactOpinion / debate
Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT sectionUnionRailwaysNot yet verifiedNew Saphale (Vaitarna) to Jawaharlal Nehru Port, 102.9 km, MaharashtraDedicated Freight Corridor Corporation of India Ltd (DFCCIL)Completed· 365 days lateCompleted100% done
Completed31 Mar 2026

Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT section

All key dates

  1. Original target31 Mar 2025
  2. Revised target31 Dec 2025
  3. Second revised target31 Mar 2026
  4. Completed31 Mar 2026
———Land acquisition and encroachments, then pending signalling and overhead electrification works.—
Delhi–Ghaziabad–Meerut Namo Bharat (RRTS) corridorUnionUrban transportNot yet verifiedSarai Kale Khan (Delhi) to Modipuram (Meerut), 82 kmNational Capital Region Transport Corporation (NCRTC)CompletedCompleted100% done
Completed22 Feb 2026

Delhi–Ghaziabad–Meerut Namo Bharat (RRTS) corridor

All key dates

  1. Priority section opened20 Oct 2023
  2. Completed22 Feb 2026
Sanctioned: ₹30,274 cr————
Udhampur–Srinagar–Baramulla Rail Link (USBRL)UnionRailwaysNot yet verifiedUdhampur to Baramulla, 272 km, Jammu and KashmirNorthern RailwayCompleted· 6489 days lateCompleted100% done
Completed6 Jun 2025

Udhampur–Srinagar–Baramulla Rail Link (USBRL)

All key dates

  1. Original target31 Aug 2007
  2. Completed6 Jun 2025
Sanctioned: ₹1,500 crRevised: ₹43,780 cr————
New Pamban rail bridgeUnionRailwaysNot yet verifiedMandapam to Rameswaram (Pamban island), Ramanathapuram district, Tamil NaduRail Vikas Nigam Ltd (RVNL)CompletedCompleted100% done
Completed6 Apr 2025

New Pamban rail bridge

All key dates

  1. Completed6 Apr 2025
Spent: ₹535 cr—————

Know a project that is missing?

Tell us the project's name, place, budget, dates and status, and link to proof (a government order, tender notice, news report or photo). The admin checks it before it appears.

Sign in to report a project or an update.

Only real projects are listed. Every project links to its source: an official dataset or document, or evidence shared by a member. Each stays marked “Not yet verified” until the admin has checked it. Schedule health is calculated automatically from the published dates and progress.