Project tracker
Public projects announced or started by the Union, State, district, tehsil/taluka and local governments: budget, contractor, key dates, officer in charge, progress, and where and why a project is stuck.
Ongoing projects (4)
Swipe sideways to see all columns →
| Project | Status | Key date | Budget | Tender awarded to | Officer in charge | Where it is stuck · why | Environmental impact | Opinion / debate |
|---|---|---|---|---|---|---|---|---|
| Mumbai–Ahmedabad High Speed Rail (bullet train)UnionRailwaysNot yet verifiedMumbai (Bandra-Kurla Complex) to Sabarmati (Ahmedabad), 508 kmNational High Speed Rail Corporation Ltd (NHSRCL) | Delayed· 2192 days lateWork in progress61% done | Target31 Dec 2029Originally 31 Dec 2023 Mumbai–Ahmedabad High Speed Rail (bullet train) All key dates
| Sanctioned: ₹1,08,000 crSpent: ₹90,966 cr | — | — | Delay in land acquisition in Maharashtra and the resulting delay in awarding contracts, and the impact of COVID-19 (Government's answer in the Rajya Sabha, 31 March 2023). | In 2022 the Bombay High Court allowed about 22,000 mangrove trees to be cut for the corridor (about 13.4 hectares of mangrove land affected), with replanting at a 1:5 ratio. In August 2026 it allowed 847 more mangroves to be cut for a power line feeding the corridor in Palghar, but said replanting hundreds of kilometres away (in Solapur) does not restore the local ecology, and that it will not permit such distant compensation in future. | |
| Bengaluru Suburban Rail ProjectStateRailwaysNot yet verifiedBengaluru, KarnatakaRail Infrastructure Development Company (Karnataka) Ltd (K-RIDE) | Delayed· 1186 days lateWork in progress | Target31 Mar 2030Originally 31 Dec 2026 Bengaluru Suburban Rail Project All key dates
| Sanctioned: ₹15,767 crRevised: ₹16,876 cr | — | — | Stuck at: Corridors 2 and 4: the civil contractor (L&T) left; K-RIDE re-tendered Corridor 2The main contractor left the corridor contracts and the work had to be re-tendered; land for Corridor 1 is still to be acquired. | — | |
| Delhi–Mumbai ExpresswayUnionRoadsNot yet verifiedDelhi to Mumbai, 1,445 km including spurs (Haryana, Rajasthan, Madhya Pradesh, Gujarat, Maharashtra)National Highways Authority of India (NHAI) | Delayed· 1186 days lateWork in progress | Target31 Mar 2028Originally 31 Dec 2024 Delhi–Mumbai Expressway All key dates
| Spent: ₹71,718 cr— | — | — | Stuck at: Three Gujarat packages (87 km) on the Vadodara–Virar section, held by Roadway Solutions India Infra LtdNHAI cites the contractor's non-performance and contractual disputes on the three Gujarat packages; the contractor cites delays by NHAI in handing over land. | Near the buffer zone of Ranthambore Tiger Reserve, a 12 km stretch was built as India's first wildlife corridor on a national highway, designed with the Wildlife Institute of India: five animal overpasses and a long underpass let tigers, leopards and bears cross safely, with noise barriers along the road. It opened in June 2025. | |
| Zojila TunnelUnionRoadsNot yet verifiedBaltal (Jammu and Kashmir) to Minamarg (Ladakh)National Highways and Infrastructure Development Corporation Ltd (NHIDCL) | Delayed· 517 days lateWork in progress64% done | Target29 Feb 2028Originally 30 Sept 2026 Zojila Tunnel All key dates
| Sanctioned: ₹6,809 crSpent: ₹3,934.42 cr | — | — | COVID-19 disruptions, a terrorist attack at the nearby Sonamarg tunnel project, and long spells of harsh weather (Union Minister, Lok Sabha). | — |
Completed and closed projects (7)
Finished projects with all their details, including how late they were against the original target.
Swipe sideways to see all columns →
| Project | Status | Key date | Budget | Tender awarded to | Officer in charge | Where it is stuck · why | Environmental impact | Opinion / debate |
|---|---|---|---|---|---|---|---|---|
| Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT sectionUnionRailwaysNot yet verifiedNew Saphale (Vaitarna) to Jawaharlal Nehru Port, 102.9 km, MaharashtraDedicated Freight Corridor Corporation of India Ltd (DFCCIL) | Completed· 365 days lateCompleted100% done | Completed31 Mar 2026 Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT section All key dates
| — | — | — | Land acquisition and encroachments, then pending signalling and overhead electrification works. | — | |
| Noida International Airport, Jewar — Phase 1StateAviationNot yet verifiedJewar, Gautam Buddh Nagar, Uttar PradeshYamuna International Airport Pvt Ltd (concessionaire); Noida International Airport Ltd (Government of Uttar Pradesh) | Completed· 544 days lateCompleted | Completed28 Mar 2026 Noida International Airport, Jewar — Phase 1 All key dates
| Sanctioned: ₹10,056 cr | — | — | — | — | |
| Delhi–Ghaziabad–Meerut Namo Bharat (RRTS) corridorUnionUrban transportNot yet verifiedSarai Kale Khan (Delhi) to Modipuram (Meerut), 82 kmNational Capital Region Transport Corporation (NCRTC) | CompletedCompleted100% done | Completed22 Feb 2026 Delhi–Ghaziabad–Meerut Namo Bharat (RRTS) corridor All key dates
| Sanctioned: ₹30,274 cr | — | — | — | — | |
| Navi Mumbai International Airport — Phase 1StateAviationNot yet verifiedNavi Mumbai, Raigad district, MaharashtraNavi Mumbai International Airport Pvt Ltd (Adani Airports Holdings and CIDCO) | CompletedCompleted100% done | Completed8 Oct 2025 Navi Mumbai International Airport — Phase 1 All key dates
| Spent: ₹19,650 cr— | — | — | — | The site needed the Ulwe river to be diverted, a hill to be levelled and mangroves on the site to be cleared. The environmental clearance (2010) came with 32 conditions, including compensatory mangrove planting (about 350 hectares at Dahanu); the Gadhi river was left untouched after the runway layout was changed. Environmentalists warned of flood risk in the low-lying area. | |
| Udhampur–Srinagar–Baramulla Rail Link (USBRL)UnionRailwaysNot yet verifiedUdhampur to Baramulla, 272 km, Jammu and KashmirNorthern Railway | Completed· 6489 days lateCompleted100% done | Completed6 Jun 2025 Udhampur–Srinagar–Baramulla Rail Link (USBRL) All key dates
| Sanctioned: ₹1,500 crRevised: ₹43,780 cr | — | — | — | — | |
| New Pamban rail bridgeUnionRailwaysNot yet verifiedMandapam to Rameswaram (Pamban island), Ramanathapuram district, Tamil NaduRail Vikas Nigam Ltd (RVNL) | CompletedCompleted100% done | Completed6 Apr 2025 New Pamban rail bridge All key dates
| Spent: ₹535 cr— | — | — | — | — | |
| Atal Setu (Mumbai Trans Harbour Link)StateRoadsNot yet verifiedSewri (Mumbai) to Nhava Sheva (Navi Mumbai), MaharashtraMumbai Metropolitan Region Development Authority (MMRDA) | CompletedCompleted100% done | Completed12 Jan 2024 Atal Setu (Mumbai Trans Harbour Link) All key dates
| Spent: ₹17,840 cr— | — | — | — | The bridge crosses the Sewri mudflats, an Important Bird Area where flamingos feed. MMRDA did not accept the Bombay Natural History Society's request to shift the alignment, and instead used noise barriers, low-vibration drilling and warm, shielded lighting; officials reported that flamingos kept visiting during construction. Activists say the bird sanctuaries planned at nearby wetlands as part of the mitigation have not been set up. |