Project tracker
Public projects announced or started by the Union, State, district, tehsil/taluka and local governments: budget, contractor, key dates, officer in charge, progress, and where and why a project is stuck.
Ongoing projects (5)
Swipe sideways to see all columns →
| Project | Status | Key date | Budget | Tender awarded to | Officer in charge | Where it is stuck · why | Environmental impact | Opinion / debate |
|---|---|---|---|---|---|---|---|---|
| Vadhavan PortUnionPortsNot yet verifiedVadhavan, Dahanu, Palghar district, MaharashtraVadhavan Port Project Ltd (JNPA 74%, Maharashtra Maritime Board 26%) | On trackWork in progress | Target31 Dec 2030 Vadhavan Port All key dates
| Sanctioned: ₹76,220 cr | — | — | — | Dahanu taluka is a notified ecologically fragile area. To reduce harm, the port was moved 4–6 km out to sea, which also limited land acquisition to about 571 hectares for road and rail links. It received environmental and coastal (CRZ) clearance in February 2024 and a conditional no-objection from the Dahanu Taluka Environment Protection Authority, which set up monitoring and grievance committees. Local fishing communities oppose it, citing their fishing grounds, mangroves near the site and protected corals recorded in surveys. | |
| Chennai Metro Rail Phase IIStateUrban transportNot yet verifiedChennai, Tamil NaduChennai Metro Rail Ltd (CMRL) | On trackWork in progress | Target31 Dec 2027 Chennai Metro Rail Phase II All key dates
| Sanctioned: ₹63,246 cr | — | — | — | — | |
| Ken–Betwa Link ProjectUnionIrrigationNot yet verifiedDaudhan dam on the Ken (Madhya Pradesh) and link canal to the Betwa; Bundelkhand (Madhya Pradesh and Uttar Pradesh)Ken-Betwa Link Project Authority (KBLPA) | On trackWork in progress | Target31 Mar 2030 Ken–Betwa Link Project All key dates
| Sanctioned: ₹44,605 crSpent: ₹11,379.74 cr | NCC Ltd (Daudhan dam) | — | — | The Daudhan reservoir submerges part of the Panna Tiger Reserve: the National Water Development Agency puts it at about 41 sq km, while independent studies estimate more. Official documents in 2017 estimated about 18 lakh trees would be felled or affected. Wildlife experts warn of harm to tigers, gharials and vultures downstream. About 1,913 families in 10 villages are to be rehabilitated, and cases are pending before the National Green Tribunal and the Supreme Court. | |
| Polavaram Irrigation ProjectStateIrrigationNot yet verifiedPolavaram, on the Godavari, Andhra PradeshWater Resources Department, Government of Andhra Pradesh | On trackWork in progress | Target31 Dec 2027 Polavaram Irrigation Project All key dates
| — | — | — | — | The reservoir submerges about 276 villages in Andhra Pradesh by government estimates, plus villages in Odisha and Chhattisgarh, displacing many families, a majority of them Koya and Konda Reddi tribal people. It also submerges parts of the Papikonda National Park. The Union environment ministry approved diverting 3,731 hectares of forest land for the project in July 2010. | |
| Medigadda (Lakshmi) barrage restoration, Kaleshwaram projectStateIrrigationNot yet verifiedMedigadda (Lakshmi) barrage on the Godavari, TelanganaIrrigation and Command Area Development Department, Government of Telangana | On trackAnnounced | Target30 Jun 2027 Medigadda (Lakshmi) barrage restoration, Kaleshwaram project All key dates
| — | — | — | Stuck at: Restoration designs to follow CWC and NDSA recommendations; over ₹800 crore of contractor bills pendingThe barrage cannot be used until Block 7 is rebuilt. Responsibility for the restoration cost is disputed between the State and the original contractor. | — |
Completed and closed projects (7)
Finished projects with all their details, including how late they were against the original target.
Swipe sideways to see all columns →
| Project | Status | Key date | Budget | Tender awarded to | Officer in charge | Where it is stuck · why | Environmental impact | Opinion / debate |
|---|---|---|---|---|---|---|---|---|
| Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT sectionUnionRailwaysNot yet verifiedNew Saphale (Vaitarna) to Jawaharlal Nehru Port, 102.9 km, MaharashtraDedicated Freight Corridor Corporation of India Ltd (DFCCIL) | Completed· 365 days lateCompleted100% done | Completed31 Mar 2026 Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT section All key dates
| — | — | — | Land acquisition and encroachments, then pending signalling and overhead electrification works. | — | |
| Noida International Airport, Jewar — Phase 1StateAviationNot yet verifiedJewar, Gautam Buddh Nagar, Uttar PradeshYamuna International Airport Pvt Ltd (concessionaire); Noida International Airport Ltd (Government of Uttar Pradesh) | Completed· 544 days lateCompleted | Completed28 Mar 2026 Noida International Airport, Jewar — Phase 1 All key dates
| Sanctioned: ₹10,056 cr | — | — | — | — | |
| Delhi–Ghaziabad–Meerut Namo Bharat (RRTS) corridorUnionUrban transportNot yet verifiedSarai Kale Khan (Delhi) to Modipuram (Meerut), 82 kmNational Capital Region Transport Corporation (NCRTC) | CompletedCompleted100% done | Completed22 Feb 2026 Delhi–Ghaziabad–Meerut Namo Bharat (RRTS) corridor All key dates
| Sanctioned: ₹30,274 cr | — | — | — | — | |
| Navi Mumbai International Airport — Phase 1StateAviationNot yet verifiedNavi Mumbai, Raigad district, MaharashtraNavi Mumbai International Airport Pvt Ltd (Adani Airports Holdings and CIDCO) | CompletedCompleted100% done | Completed8 Oct 2025 Navi Mumbai International Airport — Phase 1 All key dates
| Spent: ₹19,650 cr— | — | — | — | The site needed the Ulwe river to be diverted, a hill to be levelled and mangroves on the site to be cleared. The environmental clearance (2010) came with 32 conditions, including compensatory mangrove planting (about 350 hectares at Dahanu); the Gadhi river was left untouched after the runway layout was changed. Environmentalists warned of flood risk in the low-lying area. | |
| Udhampur–Srinagar–Baramulla Rail Link (USBRL)UnionRailwaysNot yet verifiedUdhampur to Baramulla, 272 km, Jammu and KashmirNorthern Railway | Completed· 6489 days lateCompleted100% done | Completed6 Jun 2025 Udhampur–Srinagar–Baramulla Rail Link (USBRL) All key dates
| Sanctioned: ₹1,500 crRevised: ₹43,780 cr | — | — | — | — | |
| New Pamban rail bridgeUnionRailwaysNot yet verifiedMandapam to Rameswaram (Pamban island), Ramanathapuram district, Tamil NaduRail Vikas Nigam Ltd (RVNL) | CompletedCompleted100% done | Completed6 Apr 2025 New Pamban rail bridge All key dates
| Spent: ₹535 cr— | — | — | — | — | |
| Atal Setu (Mumbai Trans Harbour Link)StateRoadsNot yet verifiedSewri (Mumbai) to Nhava Sheva (Navi Mumbai), MaharashtraMumbai Metropolitan Region Development Authority (MMRDA) | CompletedCompleted100% done | Completed12 Jan 2024 Atal Setu (Mumbai Trans Harbour Link) All key dates
| Spent: ₹17,840 cr— | — | — | — | The bridge crosses the Sewri mudflats, an Important Bird Area where flamingos feed. MMRDA did not accept the Bombay Natural History Society's request to shift the alignment, and instead used noise barriers, low-vibration drilling and warm, shielded lighting; officials reported that flamingos kept visiting during construction. Activists say the bird sanctuaries planned at nearby wetlands as part of the mitigation have not been set up. |
Know a project that is missing?
Tell us the project's name, place, budget, dates and status, and link to proof (a government order, tender notice, news report or photo). The admin checks it before it appears.