Public projects announced or started by the Union, State, district, tehsil/taluka and local governments: budget, contractor, key dates, officer in charge, progress, and where and why a project is stuck.

Reset

Ongoing projects (5)

Swipe sideways to see all columns →

Ongoing projects
ProjectStatusKey dateBudgetTender awarded toOfficer in chargeWhere it is stuck · whyEnvironmental impactOpinion / debate
Vadhavan PortUnionPortsNot yet verifiedVadhavan, Dahanu, Palghar district, MaharashtraVadhavan Port Project Ltd (JNPA 74%, Maharashtra Maritime Board 26%)On trackWork in progress
Target31 Dec 2030

Vadhavan Port

All key dates

  1. Sanctioned19 Jun 2024
  2. Foundation stone laid by the Prime Minister30 Aug 2024
  3. Original target31 Dec 2030
Sanctioned: ₹76,220 cr———Dahanu taluka is a notified ecologically fragile area. To reduce harm, the port was moved 4–6 km out to sea, which also limited land acquisition to about 571 hectares for road and rail links. It received environmental and coastal (CRZ) clearance in February 2024 and a conditional no-objection from the Dahanu Taluka Environment Protection Authority, which set up monitoring and grievance committees. Local fishing communities oppose it, citing their fishing grounds, mangroves near the site and protected corals recorded in surveys.
Chennai Metro Rail Phase IIStateUrban transportNot yet verifiedChennai, Tamil NaduChennai Metro Rail Ltd (CMRL)On trackWork in progress
Target31 Dec 2027

Chennai Metro Rail Phase II

All key dates

  1. Sanctioned3 Oct 2024
  2. Original target31 Dec 2027
Sanctioned: ₹63,246 cr————
Ken–Betwa Link ProjectUnionIrrigationNot yet verifiedDaudhan dam on the Ken (Madhya Pradesh) and link canal to the Betwa; Bundelkhand (Madhya Pradesh and Uttar Pradesh)Ken-Betwa Link Project Authority (KBLPA)On trackWork in progress
Target31 Mar 2030

Ken–Betwa Link Project

All key dates

  1. Contract awarded28 Nov 2024
  2. Foundation stone laid by the Prime Minister25 Dec 2024
  3. Original target31 Mar 2030
Sanctioned: ₹44,605 crSpent: ₹11,379.74 crNCC Ltd (Daudhan dam)——The Daudhan reservoir submerges part of the Panna Tiger Reserve: the National Water Development Agency puts it at about 41 sq km, while independent studies estimate more. Official documents in 2017 estimated about 18 lakh trees would be felled or affected. Wildlife experts warn of harm to tigers, gharials and vultures downstream. About 1,913 families in 10 villages are to be rehabilitated, and cases are pending before the National Green Tribunal and the Supreme Court.
Polavaram Irrigation ProjectStateIrrigationNot yet verifiedPolavaram, on the Godavari, Andhra PradeshWater Resources Department, Government of Andhra PradeshOn trackWork in progress
Target31 Dec 2027

Polavaram Irrigation Project

All key dates

  1. Original target31 Dec 2027
————The reservoir submerges about 276 villages in Andhra Pradesh by government estimates, plus villages in Odisha and Chhattisgarh, displacing many families, a majority of them Koya and Konda Reddi tribal people. It also submerges parts of the Papikonda National Park. The Union environment ministry approved diverting 3,731 hectares of forest land for the project in July 2010.
Medigadda (Lakshmi) barrage restoration, Kaleshwaram projectStateIrrigationNot yet verifiedMedigadda (Lakshmi) barrage on the Godavari, TelanganaIrrigation and Command Area Development Department, Government of TelanganaOn trackAnnounced
Target30 Jun 2027

Medigadda (Lakshmi) barrage restoration, Kaleshwaram project

All key dates

  1. Pier 20 of Block 7 sank21 Oct 2023
  2. NDSA final report24 Apr 2025
  3. Original target30 Jun 2027
———Stuck at: Restoration designs to follow CWC and NDSA recommendations; over ₹800 crore of contractor bills pendingThe barrage cannot be used until Block 7 is rebuilt. Responsibility for the restoration cost is disputed between the State and the original contractor.—

Completed and closed projects (7)

Finished projects with all their details, including how late they were against the original target.

Swipe sideways to see all columns →

Completed and closed projects
ProjectStatusKey dateBudgetTender awarded toOfficer in chargeWhere it is stuck · whyEnvironmental impactOpinion / debate
Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT sectionUnionRailwaysNot yet verifiedNew Saphale (Vaitarna) to Jawaharlal Nehru Port, 102.9 km, MaharashtraDedicated Freight Corridor Corporation of India Ltd (DFCCIL)Completed· 365 days lateCompleted100% done
Completed31 Mar 2026

Western Dedicated Freight Corridor: New Saphale (Vaitarna)–JNPT section

All key dates

  1. Original target31 Mar 2025
  2. Revised target31 Dec 2025
  3. Second revised target31 Mar 2026
  4. Completed31 Mar 2026
———Land acquisition and encroachments, then pending signalling and overhead electrification works.—
Noida International Airport, Jewar — Phase 1StateAviationNot yet verifiedJewar, Gautam Buddh Nagar, Uttar PradeshYamuna International Airport Pvt Ltd (concessionaire); Noida International Airport Ltd (Government of Uttar Pradesh)Completed· 544 days lateCompleted
Completed28 Mar 2026

Noida International Airport, Jewar — Phase 1

All key dates

  1. Original target30 Sept 2024
  2. Aerodrome licence6 Mar 2026
  3. Completed28 Mar 2026
  4. Commercial flights scheduled to begin15 Jun 2026
Sanctioned: ₹10,056 cr————
Delhi–Ghaziabad–Meerut Namo Bharat (RRTS) corridorUnionUrban transportNot yet verifiedSarai Kale Khan (Delhi) to Modipuram (Meerut), 82 kmNational Capital Region Transport Corporation (NCRTC)CompletedCompleted100% done
Completed22 Feb 2026

Delhi–Ghaziabad–Meerut Namo Bharat (RRTS) corridor

All key dates

  1. Priority section opened20 Oct 2023
  2. Completed22 Feb 2026
Sanctioned: ₹30,274 cr————
Navi Mumbai International Airport — Phase 1StateAviationNot yet verifiedNavi Mumbai, Raigad district, MaharashtraNavi Mumbai International Airport Pvt Ltd (Adani Airports Holdings and CIDCO)CompletedCompleted100% done
Completed8 Oct 2025

Navi Mumbai International Airport — Phase 1

All key dates

  1. Completed8 Oct 2025
  2. Commercial flights began25 Dec 2025
Spent: ₹19,650 cr————The site needed the Ulwe river to be diverted, a hill to be levelled and mangroves on the site to be cleared. The environmental clearance (2010) came with 32 conditions, including compensatory mangrove planting (about 350 hectares at Dahanu); the Gadhi river was left untouched after the runway layout was changed. Environmentalists warned of flood risk in the low-lying area.
Udhampur–Srinagar–Baramulla Rail Link (USBRL)UnionRailwaysNot yet verifiedUdhampur to Baramulla, 272 km, Jammu and KashmirNorthern RailwayCompleted· 6489 days lateCompleted100% done
Completed6 Jun 2025

Udhampur–Srinagar–Baramulla Rail Link (USBRL)

All key dates

  1. Original target31 Aug 2007
  2. Completed6 Jun 2025
Sanctioned: ₹1,500 crRevised: ₹43,780 cr————
New Pamban rail bridgeUnionRailwaysNot yet verifiedMandapam to Rameswaram (Pamban island), Ramanathapuram district, Tamil NaduRail Vikas Nigam Ltd (RVNL)CompletedCompleted100% done
Completed6 Apr 2025

New Pamban rail bridge

All key dates

  1. Completed6 Apr 2025
Spent: ₹535 cr—————
Atal Setu (Mumbai Trans Harbour Link)StateRoadsNot yet verifiedSewri (Mumbai) to Nhava Sheva (Navi Mumbai), MaharashtraMumbai Metropolitan Region Development Authority (MMRDA)CompletedCompleted100% done
Completed12 Jan 2024

Atal Setu (Mumbai Trans Harbour Link)

All key dates

  1. Completed12 Jan 2024
Spent: ₹17,840 cr————The bridge crosses the Sewri mudflats, an Important Bird Area where flamingos feed. MMRDA did not accept the Bombay Natural History Society's request to shift the alignment, and instead used noise barriers, low-vibration drilling and warm, shielded lighting; officials reported that flamingos kept visiting during construction. Activists say the bird sanctuaries planned at nearby wetlands as part of the mitigation have not been set up.

Know a project that is missing?

Tell us the project's name, place, budget, dates and status, and link to proof (a government order, tender notice, news report or photo). The admin checks it before it appears.

Sign in to report a project or an update.

Only real projects are listed. Every project links to its source: an official dataset or document, or evidence shared by a member. Each stays marked “Not yet verified” until the admin has checked it. Schedule health is calculated automatically from the published dates and progress.